The construction update for Backstage Condominium, 1 The Esplanade,
July 16 – 22, 2016 is posted at http://ltowerconstructioninfo.com
Backstage construction work has faced some slight delays in the past
week as a result of the heavy rain and extreme heat. Work crews will
be coming in earlier, within the permitted construction work hours, to
help make up for this.
This week and next prep work for the east side porcelain tile panel
backing continues to progresses with preparing the east side: crews
have been measuring and aligning their assemblies to be ready for the
tile installation.
Installation of porcelain tile on the west side of the tower is making
steasy progress and continues through next week.
The north face of the podium is also progressing. Crews are
installing some of the special cut pieces to complete the facade.
Other work that is ongoing includes: applying finishes to the balcony
floors; applying finishes to floors on the 7th and 6th amenity levels.
Suite inspections are continuing past for the remaining Hoist Suites
(east tower) and some sites at the Amenity levels (7th and 6th floors.
Please check back at http://ltowerconstructioninfo.com for regular updates.