The city has completed an investigation of options for increasing the capacity of the Island Water Treatment Plant, located on the south side of Toronto Islands.

The study has determined that the preferred solution is to maximize the production capacity and treatment performance of the existing infrastructure at the Island Water Treatment Plant to increase its capacity from 410 million litres per day to 450 million litres per day, or nearly 10%.

A project file report documenting the environmental assessment study has been completed and has been placed on public record for a 30-day review period  ending August 8. It is available for review online at www.toronto.ca/islandtp.

If you have any questions or outstanding issues about this project, contact Mike Logan at (416) 392-4360 or mlogan@toronto.ca.