City of Toronto Downtown Construction Update
www.toronto.ca/downtownconstructionprojects
Below are updates regarding the construction projects taking place downtown this spring, summer and fall.
Downtown Construction Map
UPDATES
Watermain Replacement, Streetcar Track Replacement and Road Improvements on
Dundas Street East from Yonge Street to Church Street
Start Date: April 24, 2017
NEW End Date: September 30, 2017
Location: Dundas Street East (Yonge Street – Church Street)
THE PROJECT STAGING IS CHANGING ON MONDAY JULY 16th
The work the City of Toronto has been delivering on Dundas Street East between Yonge Street and Church Street is progressing well. From July 16 to September 17, the contractor, working with the Toronto Transit Commission will replace the streetcar tracks at Victoria Street/Dundas Street East/Dundas Square.
To accommodate the streetcar track replacement work, three lanes of Dundas Street will be completely closed. Only one lane of westbound traffic will be open on Dundas Street East from Church to Yonge Street. There will also be closures on Victoria Street, this will impact access to Dundas Square.
Further staging and traffic restriction details are available online in Construction Update #1
TTC Construction Notice
Wellington Street Watermain Replacement & Streetcar Track Reconstruction
Planned start date: April 10, 2017
Planned End Date: October 27, 2017
NEW End Date: Mid-Late August 2017
Location: Wellington St From York Street To Church Street
UPDATE: July 14, 2017
Work on Wellington is progressing well. There is one section of watermain between Bay Street and York street that is currently being flushed and tested. This is the last remaining section of the new watermain that has yet to pass testing. When the section passes, crews will reconstruct this portion of road. The watermain from Bay to Church and the TTC track work from York to Yonge and streetscape work is now complete. To date the Wellington project is on schedule.
Notices & Updates
Construction Update #3
Construction Update #2
Construction Update #1
Pre-Construction Notice
Construction Notice
F.G. Gardiner Expressway Lower Simcoe Ramp Removal & Harbour Street Improvements
Start Date: April 2017
Planned End Date: January 2018
Location: Lower Simcoe/Harbour Street
The demolition of the York-Bay-Yonge ramp is now complete. Work started on April 17th and the demolition was completed ahead of schedule. We appreciate the patience of residents and businesses in the neighbourhood during this stage of work.
Eastbound on-ramp at Rees Street
In order to construct the new ramp, the eastbound on-ramp at Rees Street will need to be closed intermittently, Monday to Saturday, 9:30 a.m. to 3:30 p.m. for the next 4 weeks to allow work to take place during the day and reduce overnight work.
On Saturdays the eastbound on-ramp will be closed at 7 a.m. and will reopen at 1p.m.
Information regarding the remaining pier columns can be found here
For more information please see: FG Gardiner Ramp Removal and Harbour Street Improvements Project Website
College St BIA Streetscaping (Havelock St to Shaw St)Start Date: June 19, 2017
NEW End Date: October 13, 2017
Location: College St. between Havelock and Shaw
Work on Stage 2 started
We are pleased to report that stage 2 began ahead of schedule on July 10th. Work is progressing well despite a few days of inclement weather.
Weekend Work Scheduling
Saturday work hours are from 7:00 a.m. to 2:00 p.m. The contractor has agreed to not do any heavy breaking or machinery moving between 7:00 a.m. and 9:00 a.m.; however at 9:00 a.m. louder operations may occur on Saturdays.
For local updates and more information please see: College Street Construction
Queen Street West Streetscaping
Start Date: June 19, 2017
Planned End Date: November 30, 2017
Location: Bathurst St to Spadina Ave.
The sidewalk on the south side of Queen Street West, from Bathurst Street to Portland Street has been fully reconstructed. Half of the sidewalk on Queen Street West from Portland Street to Augusta Avenue has been completed as well. The Streetscaping project is still on schedule for completion. Streetscaping along Queen Street West from Bathurst Street to Spadina Avenue will include new tree plantings, street lighting and public art. |